Top performers of PM Suryaghar Muft Bijli Yojna (PMS-MBY)
Out of the total applications for installations, 37% have been executed by December 2025, a jump of 10% from October 2025 and 18% from July 2025 . This is majorly due to a decline of around 1 million applications in November 2025. Check here โ https://tinyurl.com/3enfwk95
๐ฉ Gujarat, Maharashtra, Uttar Pradesh and Kerala have been top performers in gross installations since the launch of PMS-MBY.
Capacity addition between August and December 2025
- Maharashtra added 525 MW at a growth rate of 56%
- Uttar Pradesh โ 488 MW at a growth rate of 77%
- Gujarat โ 438 MW at a growth rate of 29%
- Kerala โ 204 MW at a growth rate of 41%
- Rajasthan โ 204 MW at a growth rate of 75%
๐ฉ For the month of December 2025, Gujarat, Uttar Pradesh and Maharashtra stay the top 3 installers.
Capacity addition in December 2025
- Gujarat and Uttar Pradesh running neck to neck, both adding 108 MW
- Maharashtra added 97 MW
- Rajasthan added 50 MW
- Kerala added 41 MW